Work schedules
We will post additional highlights of pending and completed work activities on this page regularly once work begins.
Implementation Timeline and Key Events
We will post additional highlights of pending and completed work activities on this page regularly once work begins.
• Fall 2025: Preparation Work for UDF construction
• April 2026: Submission of Reach 5A RD/RA Work Plan for EPA review
• May 2026: Construction of UDF begins
• Fall 2027: Reach 5A Preparation Work begins
• Summer 2028: Reach 6 Preparation Work begins
• Early Summer 2028: Reach 5A sediment/soil removal begins*
• Early Summer 2029: Reach 6 sediment/soil removal begins*
*Tentative, subject to change.